Sunday, October 17 – Saturday, October 23, 2021:
-
Installation of traffic street names at Raleigh Street SE, Randle Place SE, Lebaum Street SE, and Milwaukee Place SE.
-
Installation of the trench drain to the bio retentions between Randle Place SE and Raleigh Street SE on southbound Martin Luther King Jr. Avenue SE.
-
Installation of metal trench drain covers for the bio retentions between Randle Place SE and Raleigh Street SE on southbound Martin Luther King Jr. Avenue SE.
-
Worked on ADA ramp, gutter pan, PCC sidewalk and other punch list items at the fire station on Martin Luther King Jr. Avenue SE.
Sunday, October 10 – Saturday, October 16, 2021:
-
Fixing bolt covers and traffic signal light in the southeast corner of 5th Street SE.
-
Installation of traffic street names at Raleigh Street SE Lebaum Street SE.
Sunday, October 3 – Saturday, October 9, 2021:
-
Installation of 4 signs and removal of 3 signs on Martin Luther King Jr. Avenue SE to Cypress Street SE.
-
Preparation of area for pervious concrete repairs on Martin Luther King Jr. Avenue SE at multiple locations between 4th Street SE to Milwaukee Place SE.