REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
DECEMBER 2020
Sunday, December 27 – Saturday, January 2, 2021:
-
Placement of stones for pervious sidewalk northbound between 4th Street SE and 5th Street SE.
-
Removal of the maintenance of traffic (MOT) layout between Cypress Street SE to the end of project.
-
Installation of temporary pavement markings between Raleigh Street SE, Randle Place SE and from Lebaum Street SE to Cypress Street SE.
-
Saw cut for median work at intersection between Lebaum Street SE and Cypress Street SE.
-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Excavation for planting soil and pervious sidewalk at northbound between 4th Street SE and 5th Street SE.
-
Stripping of lines for phase 4 between Randle Place SE and Lebaum Street SE.
-
Installation of granite curb, gutter and wheelchair ramp at northbound between 4th Street SE to 5th Street SE.
-
Installation of plain cement concrete (PCC) sidewalk for the walkway in front of the church at Martin Luther King Jr. Avenue SE between 4th Street SE and 5th Street SE.
-
Installation granite curb for median between Lebaum Street SE and Cypress Street SE
-
Restoration of plain cement concrete (PCC) for electrical conduits trench at the intersection of Milwaukee Place SE and Martin Luther King Jr. Avenue SE.
-
Installation of traffic signal foundations northbound Martin Luther King Jr. Avenue SE, at the intersection of 5th Street SE and Martin Luther King Jr. Avenue SE and between Cypress Street SE and Milwaukee Street SE.
-
Installation of the bio-retention media at Martin Luther King Jr. Avenue SE northbound between 4th Street SE and 5th Street SE.
-
Saw cutting from Malcolm Avenue SE and Mellon Street SE for median work.
-
Set up maintenance of traffic (MOT) for median work from Malcolm Avenue SE to Lebaum Street SE.
-
Adjustment of a manhole at Martin Luther King Jr. Avenue SE between Cypress Street SE and Milwaukee Street SE.
-
Placement of temporary asphalt for the pavement restoration at Martin Luther King Jr. Avenue SE.
Sunday, December 20 – Saturday, December 26, 2020:
-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Preparation of sidewalk concrete on the northbound Martin Luther King Jr. Avenue SE.
-
Parging and cleaning sewer manholes located from Raleigh Street SE, Malcolm Avenue SE and southbound Martin Luther King Jr. Avenue SE.
-
Installation of concrete sidewalk at Cypress Street SE and northbound Milwaukee Place SE.
-
Placement of new bus stop pad at Lebaum Street SE and northbound Martin Luther King Jr. Avenue SE.
-
Placement of concrete for bio retention facility.
-
Installation of plain cement concrete (PCC) driveway at fire station.
Sunday, December 13 – Saturday, December 19, 2020:
-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Continued parging inside northbound Martin Luther King Jr. Avenue SE.
-
Continued to excavate work area for construction of sidewalk and planting area, northbound Martin Luther King Jr. Avenue SE.
-
Placement of plain cement concrete (PCC) and constructing repairs for 6 driveways.
-
Placement of PVE underdrain connect pipe on 5th Street SE and Alabama Avenue SE.
-
Cleaning sewer manholes located on 5th Street SE and southbound Martin Luther King Jr. Avenue SE.
-
Placement of plain cement concrete (PCC) sidewalk as field modification located on 5th Street SE and Alabama Avenue SE.
Sunday, December 6 – Saturday, December 12, 2020:
-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Continued construction for the planter bio between 4th Street SE, 5th Street SE and northbound Martin Luther King Jr. Avenue SE.
-
Cleaning, patching and construction inverts sewer manholes located from Cypress Street, northbound Malcolm X Avenue SE and southbound Martin Luther King Jr. Avenue SE.
-
Installation of PVC electrical conduit at northbound Martin Luther King Jr. Avenue SE and 5th Street SE.
-
Installation of granite curb at northbound Martin Luther King Jr. Avenue SE, 4th Street SE and 5th Street SE.
-
Installation of plain cement concrete (PCC) gutter at northbound Martin Luther King Jr. Avenue SE, 4th Street SE and 5th Street SE.
-
Excavation started on pervious concrete sidewalk northbound Martin Luther King Jr. Avenue SE.
-
Installation ADA ramp at the corner of 5th Street SE and northbound Alabama Avenue SE.
-
Installation of plain cement concrete (PCC) base at 4th Street SE and southbound Milwaukee Place SE.
-
Installation of temporary paint at 5th Street SE and Alabama Avenue SE.
-
Installation of plain cement concrete (PCC) traffic foundation at directional median 5th Street SE.
Sunday, November 29 – Saturday, December 5, 2020:
-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Completed the parging and cleaning sewer manholes located from Raleigh Street SE, Malcolm X Avenue SE and southbound Martin Luther King Jr. Avenue SE.
-
Installation of pervious sidewalk from Milwaukee Place SE, Cypress Street SE and Lebaum Street SE.
-
Switched traffic lanes at northbound Martin Luther King Jr. Avenue SE and 5th Street SE island.
-
Installation of plain cement concrete (PCC) sidewalk at various locations at Martin Luther King Jr. Avenue SE. between Milwaukee Place SE and Lebaum Street SE.
-
Removal of tree northbound Martin Luther King Jr. Avenue SE.
-
Completed the cleaning and patching of sewers and newly installed manholes located at various locations.
-
Continued construction for bio retention structure at 5th Street SE and northbound Martin Luther King Jr. Avenue SE.