REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
APRIL 2021
Sunday, April 25 – Saturday, May 1, 2021:






-
Installation and activation of the traffic signal devices and signal fixtures at the intersection of Martin Luther King Jr. Avenue SE, Randle Street SE and 5th Street SE eastbound.
-
Milling performed from the intersection of Martin Luther King Jr. Avenue SE and Milwaukee Place SE to the intersection of Martin Luther King Jr. Avenue SE and Lebaum Street SE and Malcolm X Avenue southbound.
-
Construction on pervious sidewalk and bio-retention basins between Raleigh Street SE and northbound Randle Place SE.
Sunday, April 18 – Saturday, April 24, 2021:






-
Installation of traffic signal fiber optic cable toward traffic cabinets at intersection of 5th Street SE and 4th Street SE intersection.
-
Construction of pervious sidewalk and bio-retention basins between Raleigh Place SE and northbound Randle Place SE.
-
Saw cut plain cement concrete (PCC) bus pad at 5th Street SE northbound of Martin Luther King Jr. Avenue SE.
-
Demolish and replace marked locations at plain cement concrete (PCC) bus pad at 5th Street SE.
-
Placement of traffic signal devices and signal fixtures at the intersection of Raleigh Place SE and northbound Randle Place SE.
Sunday, April 11 – Saturday, April 17, 2021:






-
Placement of reinforced steel at pedestal signal and light foundation located at the intersection of Martin Luther King Jr. Avenue SE and Cypress Street SE.
-
Installation of a 20-foot steel traffic signal pole at Martin Luther King Jr. Avenue SE and Mellon Street SE intersection, Malcolm X Avenue SE and Lebaum Street SE.
-
Installation of an 8-foot arm on pendant pole at Martin Luther King Jr. Avenue SE. and Mellon Street intersection, Malcolm X Avenue SE, Lebaum Street SE and Milwaukee Street SE.
-
Installation of a 28-foot pendant post streetlight at Martin Luther King Jr. Avenue SE and Mellon Street SE intersection.
-
Installation of pull box at Milwaukee Place SE southbound and Cypress Street SE.
-
Installation of sectional conventional pedestrian signal head at 5th Street SE intersection.
-
Installation of overlay white walking person and Portland orange at 5th Street SE intersection.
-
Installation the conductor stranded electrical traffic signal cable at 5th Street SE intersection.
-
Installation of red, green and yellow ball led module at 4th Street SE intersection and 5th Street SE intersection.
-
Installation at Portland orange countdown led at 4th Street SE intersection and 5th Street SE intersection.
-
Installation of yellow and green arrow let module at 4th Street SE intersection.
-
Installation of 3 and 5 section conventional traffic signal head at 4th Street SE intersection.
-
Installation of accessible pedestrian signal unit at 4th Street SE intersection.
-
Installation of plain cement concrete (PCC) sidewalk at Cypress Street SE. northbound and Milwaukee Place SE southbound.
-
Installation of plain cement concrete (PCC) wheelchair and bicycle ramp.
-
Placement of concrete collar on the RCP leak and repairing at northbound Martin Luther King Jr. Avenue SE.
-
Demolish and backfill the old Pepco vault on westbound 5th Street SE.
Sunday, April 4 – Saturday, April 10, 2021:






-
Plant trees in various locations northbound and southbound of Martin Luther King Jr. Avenue SE from 4th Street SE to Cypress Street SE.
-
Pull wire at traffic T-basis at Malcolm X Avenue SE intersection and 5th Street SE intersection.
-
Set poles at Martin Luther King Jr. Avenue SE and 4th Street SE, 5th Street SE and Raleigh Street SE.
-
Set up forms for the plain cement concrete (PCC) foundation on the northbound corners of northbound Martin Luther King Jr. Avenue SE and eastbound Cypress Street SE.