MAY 2021

Sunday, May 23 – Saturday, May 29, 2021:

  • Installation of stranded wire and stranded ground wire at Martin Luther King Jr. Avenue SE and Randle Street, SE and Martin Luther King Jr. Avenue SE and Lebaum Street SE.

  • Installation of fire hydrant at Martin Luther King Jr. Avenue SE northbound after Cypress Street SE.

  • Installation of various traffic signal items at various locations.

  • Installation of pavement marking line and symbols at Martin Luther King Jr. Avenue SE from 4th Street SE to Malcolm Avenue SE and from Raleigh Street SE to 5th Street SE.

  • Installation of conduits at southbound Martin Luther King Jr. Avenue SE and 4th Street SE and at the Fire Department station.

  • Installation of bike racks on northbound Martin Luther King Jr. Avenue SE from 4th Street SE to Malcolm X Avenue SE.

Sunday, May 16 – Saturday, May 22, 2021:

  • Installation of pavement marking symbols at southbound Martin Luther King Jr. Avenue SE and Mellon Street SE, northbound Martin Luther King Jr. Avenue SE,  Malcolm X Avenue SE and Parkland Street SE.

  • Installation of plain cement concrete (PCC) sidewalk at northbound Martin Luther King Jr. Avenue SE and 5th Street SE, northbound Martin Luther King Jr. Avenue SE and the alley at Parkland Street SE, northbound Martin Luther King Jr. Avenue SE and Randle Street SE, southbound Martin Luther King Jr. Avenue SE and Esther Street SE.

  • Pulling cables from Martin Luther King Jr. Avenue SE and Cypress Street, heading toward Martin Luther King Jr. Avenue SE and Milwaukee Place SE.

  • Placement of three steel benches on northbound Martin Luther King Jr. Avenue SE between 4th Street SE and 5th Street SE.

  • Relocation of a fire hydrant at westbound Esther Street SE and southbound Martin Luther King Jr. Avenue SE.

  • Installation of trash receptacle at Randle Street SE and northbound Martin Luther King Jr. Avenue SE.

  • Salvaged multiple other receptacles southbound Martin Luther King Jr. Avenue SE and Esther Street SE.

Sunday, May 9 – Saturday, May 15, 2021:

  • Placement of asphalt on Martin Luther King Jr. Avenue SE at various locations between Milwaukee Place SE, Malcolm X Avenue SE, Raleigh Street SE to 4th Street SE and Randle Street SE in front of Crown gas station.

  • Installation of pavement marking on Martin Luther King Jr. Avenue SE between Milwaukee Place SE and Lebaum Street SE.

Sunday, May 2 – Saturday, May 8, 2021:

  • Installation of temporary pavement markings for faded temporary marking at the intersection of Martin Luther King Jr. Avenue SE and Raleigh Street SE.

  • Construction of pervious sidewalk and bio-retention basins on Martin Luther King Jr. Avenue SE between Raleigh Street SE and 5th Street northbound.

  • Placement of concrete for sidewalk on Martin Luther King Jr. Avenue SE between Raleigh Street SE and 5th Street SE northbound.

  • Placement of concrete for plain cement concrete (PCC) base for the milled location, that were due for repairs.

  • Placement of asphalt at various locations to include, northbound and southbound Martin Luther King Jr. Avenue SE between Milwaukee Place SE and Malcolm X Avenue SE.