REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
JULY 2020
Sunday, July 26 – Saturday, August 1, 2020:






-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE and Malcolm X Ave SE.
-
Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.
-
Installation of bioretention northbound Martin Luther King Jr. Avenue SE from Raleigh Street SE.
-
Installed and backfilled reinforced concrete pipe (RCP) at Martin Luther King Jr. Avenue SE and Randle Street SE.
-
Cut down trees northbound Martin Luther King Jr. Avenue SE.
-
Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE, Lebaum Street SE and 4th Street SE.
-
Placed graded aggregate base (GAB) at Raleigh Street SE and Randle Street SE.
-
Furnished and installed plain cement concrete (PCC) foundation for traffic signal, bicycle and wheelchair.
-
Installed granite curb and gutter on Martin Luther King Jr. Avenue SE, 5th Street SE and Randle Street SE.
-
Installed standard catch basin at Martin Luther King Jr. Avenue SE.
Sunday, July 19 – Saturday, July 25, 2020:






-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Installed permanent maintenance of traffic (MOT) for phase two activities.
-
Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.
-
Installed and backfilled reinforced concrete pipe (RCP) at Martin Luther King Jr. Avenue SE and Lebaum Street SE.
-
Cut down trees on northbound Martin Luther King Jr. Avenue SE.
-
Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at Raleigh Street SE and Randle Place SE.
-
Placed graded aggregate base (GAB) at Lebaum Street SE.
-
Placed plain cement concrete (PCC) base at Lebaum Street SE.
-
Installed granite curb and gutter on northbound Martin Luther King Jr. Avenue SE from 5th Street SE to Raleigh Street SE.
-
Installed triple catch basin at Martin Luther King Jr Avenue SE.
-
Furnished and installed manholes on Martin Luther King Jr. Avenue SE and Lebaum Street SE.
Sunday, July 12 – Saturday, July 18, 2020:






-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE and Malcolm X Street SE.
-
Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at the following locations:
-
Malcolm X Avenue SE
-
Lebaum Street SE
-
Mellon Street SE
-
-
Furnished and installed double catch basin on northbound Martin Luther King Jr. Avenue SE.
-
Installed and continued work on various manholes on Martin Luther King Jr. Avenue SE.
-
Placed graded aggregate base (GAB) on Martin Luther King Jr. Avenue SE and Mellon Street SE.
-
Placed plain cement concrete (PCC) base on Martin Luther King Jr. Avenue SE at various locations.
-
Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.
-
Installed reinforced concrete pipe (RCP) on Martin Luther King Jr. Avenue SE.
Sunday, July 5 – Saturday, July 11, 2020:






-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.
-
Placed graded aggregate base (GAB) at various locations on Martin Luther King Jr. Avenue SE for sewer and electric activities.
-
Placed PCC base at various locations on Martin Luther King Jr. Avenue SE for electric activities.
-
Installed RCP pipe.
-
Furnished and installed PVC conduits (duct bank) at various locations.
Sunday, June 28 – Saturday, July 4, 2020:






-
Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.
-
Installation of manhole at the intersection of Mellon Street & Martin Luther King Jr. Avenue SE on the northbound sidewalk.
-
Installation of manhole at the intersection of Lebaum Street & Martin Luther King Jr. Avenue SE on the northbound sidewalk.
-
Furnished and installed PVC conduits (duct bank) at Malcolm X Avenue and Raleigh Street on Martin Luther King Jr. Avenue SE.
-
Furnished and installed the manhole at the intersection of Malcolm X Avenue and Martin Luther King Jr. Avenue SE.
-
Placed graded aggregate base (GAB) and PCC base at manhole located at the intersection of Mellon Street and Martin Luther King Jr. Avenue SE.
-
Installed the basin connect PCC pipe to the catch basin at 5th Street and Martin Luther King Jr. Avenue SE.
-
Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.
Note: There was no construction activity on Friday, July 3rd or
Saturday, July 4th due to the Independence Day Holiday .