top of page

JULY 2020

Sunday, July 26 – Saturday, August 1, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE and Malcolm X Ave SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installation of bioretention northbound Martin Luther King Jr. Avenue SE from Raleigh Street SE.

  • Installed and backfilled reinforced concrete pipe (RCP) at Martin Luther King Jr. Avenue SE and Randle Street SE.

  • Cut down trees northbound Martin Luther King Jr. Avenue SE.

  • Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE, Lebaum Street SE and 4th Street SE.

  • Placed graded aggregate base (GAB) at Raleigh Street SE and Randle Street SE.

  • Furnished and installed plain cement concrete (PCC) foundation for traffic signal, bicycle and wheelchair.

  • Installed granite curb and gutter on Martin Luther King Jr. Avenue SE, 5th Street SE and Randle Street SE.

  • Installed standard catch basin at Martin Luther King Jr. Avenue SE.

Sunday, July 19 – Saturday, July 25, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Installed permanent maintenance of traffic (MOT) for phase two activities.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installed and backfilled reinforced concrete pipe (RCP) at Martin Luther King Jr. Avenue SE and Lebaum Street SE.

  • Cut down trees on northbound Martin Luther King Jr. Avenue SE.

  • Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at Raleigh Street SE and Randle Place SE.

  • Placed graded aggregate base (GAB) at Lebaum Street SE.

  • Placed plain cement concrete (PCC) base at Lebaum Street SE.

  • Installed granite curb and gutter on northbound Martin Luther King Jr. Avenue SE from 5th Street SE to Raleigh Street SE.

  • Installed triple catch basin at Martin Luther King Jr Avenue SE.

  • Furnished and installed manholes on Martin Luther King Jr. Avenue SE and Lebaum Street SE.

Sunday, July 12 – Saturday, July 18, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE and Malcolm X Street SE.

  • Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at the following locations:

    • Malcolm X Avenue SE

    • Lebaum Street SE

    • Mellon Street SE

  • Furnished and installed double catch basin on northbound Martin Luther King Jr. Avenue SE.

  • Installed and continued work on various manholes on Martin Luther King Jr. Avenue SE.

  • Placed graded aggregate base (GAB) on Martin Luther King Jr. Avenue SE and Mellon Street SE.

  • Placed plain cement concrete (PCC) base on Martin Luther King Jr. Avenue SE at various locations.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installed reinforced concrete pipe (RCP) on Martin Luther King Jr. Avenue SE.

Sunday, July 5 – Saturday, July 11, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Placed graded aggregate base (GAB) at various locations on Martin Luther King Jr. Avenue SE for sewer and electric activities.

  • Placed PCC base at various locations on Martin Luther King Jr. Avenue SE for electric activities.

  • Installed RCP pipe.

  • Furnished and installed PVC conduits (duct bank) at various locations.

Sunday, June 28 – Saturday, July 4, 2020: