top of page

JUNE 2020

Sunday, June 21 – Saturday, June 27, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at the following locations:​

    • Malcolm X Avenue SE

    • Lebaum Street SE

    • Mellon Street SE

    • Cypress Street/Milwaukee Place SE (northbound sidewalk)

  • Placed graded aggregate base (GAB) at Martin Luther King Jr. Avenue SE

       and Malcolm X Avenue, SE

  • Placed plain cement concrete (PCC) base at Martin Luther King Jr. Avenue SE

       and Malcolm X Avenue SE.

  • Furnished and installed manholes on Martin Luther King Jr. Avenue SE at the following locations:​

    • Mellon Street SE  

    • Lebaum Street SE

    • Malcolm X Ave SE

Sunday, June 14 – Saturday, June 20, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Furnished and installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at the following locations:

    • Esther Place SE

    • 4th Street SE

    • Cypress Street/Milwaukee Place SE (northbound sidewalk)

    • Malcolm X Avenue SE

  • Furnished and installed a sewer manhole at Martin Luther King Jr. Avenue SE and Parkland Place SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Painted 4-inch double yellow lane markings between 4th Street SE and Esther Place SE on Martin Luther King Jr. Avenue SE.

  • Placed plain cement concrete (PCC) Base at Martin Luther King Jr. Avenue SE.

  • Furnished and installed standard double catch basin at Martin Luther King Jr. Avenue SE and Esther Street SE.

Sunday, June 7 – Saturday, June 13, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Installed RCP at 4th Street SE and Martin Luther King Jr. Avenue SE.

  • Furnished and installed PVC conduits (duct bank) at 4th Street SE and Martin Luther King Jr. Avenue SE.

  • Furnished and installed electric manhole at Raleigh Street and 5th Street SE (southbound).

  • Placed PCC base at Milwaukee Place and Martin Luther King Jr. Avenue SE.

  • Furnished and installed standard double catch basin at 5th Street and Martin Luther King Jr. Avenue SE (southbound).

  • Excavated, sawcut, backfilled trenches and completed temporary restoration at various locations.

  • Installed sewer at 5th Street and Martin Luther King Jr. Avenue SE (southbound).

  • Utility work on Martin Luther King Jr. Avenue SE.

  • Placed graded aggregate base (GAB) at various locations.

Sunday, May 31 – Saturday, June 6, 2020:

  • Excavated and backfilled trenches and completed temporary restoration at various locations on northbound Martin Luther King Jr. Avenue SE.

  • Installed PVC conduits (duct bank) on Martin Luther King Jr. Avenue SE at Milwaukee Place SE and Raleigh Street SE.

  • Installed manhole at Martin Luther King Jr. Avenue SE and 4th Street SE.

  • Installed manhole at Martin Luther King Jr. Avenue SE and 5th Street SE.

  • Installed RCP from Martin Luther King Jr. Avenue SE and 4th Street SE to the catch basin.

  • Installed standard double basin on southbound Martin Luther King Jr. Avenue SE and 4th Street SE catch basin.

  • Performed test pits at Martin Luther King Jr. Avenue SE and Raleigh Street SE (next to gas station).

  • Installed sewer manholes at Martin Luther King Jr. Avenue SE and Cypress Street SE.

  • Placed graded aggregate base (GAB) at northbound Martin Luther King Jr. Avenue SE and Raleigh Street SE.

  • Placed concrete base for duct bank at various locations.

bottom of page