OCTOBER 2020

Sunday, October 25 – Saturday, October 31, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installation of straight granite curb at southbound Martin Luther King Jr. Avenue SE from eastbound Milwaukee Place SE to crosswalk.

  • Installation of plain cement concrete (PCC) gutter at southbound Martin Luther King Jr. Avenue SE and Cypress Street SE crosswalk.

  • Installation circular granite curb at southbound Martin Luther King Jr. Avenue SE and eastbound Milwaukee Place SE to crosswalk.

  • Installation wheelchair ramp at southbound Martin Luther King Jr. Avenue SE and Cypress Street SE crosswalk.

  • Installation of the plain cement concrete (PCC) traffic foundation/pendant post at corner of southbound Martin Luther King Jr. Avenue SE and eastbound Lebaum Street SE.

  • Installation traffic cabinet at the corner of southbound Martin Luther King Jr. Avenue SE and eastbound Lebaum Street SE.

  • Installation plain cement concrete (PCC) sidewalk at corner of Parkland Street SE and the corner of southbound Martin Luther King Jr. Avenue SE and eastbound Malcolm X Avenue SE.

  • Installation of pervious sidewalk at Raleigh Place SE and Martin Luther King Jr. Avenue SE sidewalk.

  • Installation of DIP from new manhole toward new catch basin, northbound 4th Street SE.

  • Installation of driveway at southbound Martin Luther King Jr. Avenue SE from Cypress Street SE.

  • Placement of plain cement concrete (PCC) base for restoration at new manhole toward new catch basin.

Sunday, October 18 – Saturday, October 24, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Placement of plain cement concrete (PCC) gutter at Lebaum Street SE and Cypress Street SE.

  • Installation of straight granite curb at northbound Martin Luther King Jr. Avenue SE, Cypress Street SE to Milwaukee Place SE.

  • Installation of plain cement concrete (PCC) gutter at northbound Martin Luther King Jr. Avenue SE, Cypress Street SE to Milwaukee Place SE, southbound Martin Luther King Jr. Avenue SE and westbound Lebaum Street SE.

  • Installation circular granite curb at northbound Martin Luther King Jr. Avenue SE, Cypress Street SE to Milwaukee Place SE.

  • Installation of wheelchair ramp at the corner of southbound Martin Luther King Jr. Avenue SE, westbound Malcolm X Avenue SE and Cypress Street SE to Milwaukee Place SE.

  • Installation of double catch basin between Cypress Street and southbound Lebaum Street SE.

  • Installation of pervious sidewalk at Raleigh Place SE and southbound Martin Luther King Jr Avenue SE sidewalk.

  • Installation of the PVC rigid electrical conduits between Cypress Street SE and southbound Lebaum Street SE.

  • Installation of plain cement concrete (PCC) for traffic signal and pendant post at the intersection of southbound Martin Luther King Jr. Avenue SE and Malcolm X Avenue SE.

Sunday, October 11 – Saturday, October 17, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installation of basin connect pipe at northbound Martin Luther King Jr. Avenue SE and Lebaum Street SE.

  • Installation of straight granite curb at northbound Martin Luther King Jr. Avenue SE from alley to Cypress Street SE, southbound Martin Luther King Jr. Avenue SE and Mellon Street SE to Malcolm X Avenue SE.

  • Installation of driveway at southbound Martin Luther King Jr. Avenue SE at the Crown gas station and northbound Martin Luther King Jr. Avenue SE.

  • Installation plain cement concrete (PCC) gutter at southbound Martin Luther King Jr. Avenue SE and northbound Martin Luther King Jr. Avenue SE from alley to Cypress Street SE.

  • Installation of circular granite curb at southbound Martin Luther King Jr. Avenue SE at the Crown gas station, the southbound corner of Martin Luther King Jr. Avenue SE and westbound Mellon Street SE.

  • Placement of concrete for the extension of L- wall at bio retentions walls on northbound Martin Luther King Jr. Avenue SE from Raleigh Street SE.

  • Installation of PVC rigid electrical conduits at northbound Lebaum Street SE and southbound Mellon Street SE.

  • Continued working on the preparation for the pervious sidewalk and planting area southbound Martin Luther King Jr. Avenue SE at Crown gas station between the driveways.

  • Installation of reinforced concrete pipe (RCP) at Lebaum Street SE towards Cypress Street SE and northbound Martin Luther King Jr. Avenue SE.

  • Replacement of existing catch basin with double catch basin at Lebaum Street SE towards Cypress Street SE and northbound Martin Luther King Jr. Avenue SE.

  • Continued working on the excavation and subgrade preparation for the pervious sidewalk and planting area southbound Martin Luther King Jr. Avenue SE from Parkland Place SE to the right side of Malcolm X Avenue SE.

  • Installation of wheelchair ramp at the corner of southbound Martin Luther King Jr. Avenue SE and westbound Mellon Street SE.

Sunday, October 4 – Saturday, October 10, 2020:

  • Set up maintenance of traffic (MOT) for utility work on Martin Luther King Jr. Avenue SE.

  • Sawcut, excavations, trench excavation, backfilling and temporary restoration at various locations.

  • Installation of basin connect pipe at northbound Martin Luther King Jr. Avenue SE and Lebaum Street SE.

  • Installation of straight granite curb at southbound and northbound Martin Luther King Jr. Avenue SE, Parkland Street SE and the north entrance of the Crown gas station.

  • Installation of plain cement concrete (PCC) gutter at southbound Martin Luther King Jr. Avenue SE, Malcolm X Avenue SE, Parkland Street SE and the north entrance of the Crown gas station.

  • Installation of circular granite curb at southbound Martin Luther King Jr. Avenue SE from Malcolm X Avenue SE to Parkland Street SE and the north entrance of the Crown gas station.

  • Installation of wheelchair ramp at southbound Martin Luther King Jr. Avenue SE, Parkland Street SE and Malcolm X Avenue SE.

  • Preparation of the excavation and subgrade for the pervious sidewalk and planting area at southbound Martin Luther King Jr. Avenue SE from 4th Street SE to the right side of Esther Place SE.

  • Installation of driveway alley entrance at southbound Martin Luther King Jr. Avenue SE at the north entrance of the Crown gas station.

  • Installation of pervious concrete sidewalk formwork at southbound Martin Luther King Jr. Avenue SE from 4th Street SE to the right side of Alabama Avenue SE and the right side of Esther Place SE.