REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
REHABILITATION OF
ANACOSTIA FREEWAY BRIDGES
OVER SOUTH CAPITOL STREET
APRIL 2020
Sunday, April 26 – Saturday, May 2, 2020:
-
Set up traffic controls for utility work on Martin Luther King Jr. Avenue SE from Lebaum Street to the entrance of St. Elizabeth.
-
Trench excavation for encased electrical conduits at various locations on northbound Martin Luther King Jr. Avenue SE.
-
Installed PVC conduits (duct bank) at various locations in the northbound lanes (left travel lanes) of Martin Luther King Jr. Avenue SE.
-
Placed temporary asphalt for each manhole roadway surface on Martin Luther King Jr. Avenue SE.
-
Placed concrete at duct bank.
-
Placed graded aggregate base and PCC base on northbound lanes of Martin Luther King Jr. Avenue SE.
-
Installed sewer manholes in the northbound lane of Martin Luther King Jr. Avenue SE.
Sunday, April 19 – Saturday, April 25, 2020:
-
Saw cutting in preparation for trench excavation for electrical conduit on Martin Luther King Jr. Avenue SE from Lebaum Street SE to Milwaukee Place SE.
-
Excavated trenches for encased electrical conduits at various locations in the northbound travel lane of Martin Luther King Jr. Avenue SE.
-
Trench backfilling and surface restoration in the northbound lane of Martin Luther King Jr. Avenue SE.
-
Installed PVC conduits (duct bank) at various locations in the northbound left travel lanes along Martin Luther King Jr. Avenue SE.
-
Installed manholes along Martin Luther King Jr. Avenue SE from Randle Street SE to Lebaum Street SE.
Sunday, April 12 – Saturday, April 18, 2020:
-
Excavation of test pits on Martin Luther King Jr. Avenue SE (left lane).
-
Installation of tree protection on Martin Luther King Jr. Avenue SE (Lebaum Street SE to Milwaukee Place SE on the northbound and southbound sides).
-
Saw cutting in preparation for trench excavation for electrical conduit installations on Martin Luther King Jr. Avenue SE (Lebaum Street SE to Milwaukee Place SE).
Sunday, April 5 – Saturday, April 11, 2020:
-
Excavation of test pits at various locations on Martin Luther King Jr. Avenue SE (4th Street SE to Raleigh Street SE)
-
Marking out of utilities.
-
Installation of erosion and sedimentation controls at catch basins on the corner of Martin Luther King Jr. Avenue SE and Raleigh Street SE.
-
Removal of tree branches damaged during heavy rain and wind from Martin Luther King Jr. Avenue SE and Raleigh Street SE.